top of page

>

>

School Decking and Canopies

School Decking and Canopies

Substructure & Decking

Location

Auckland

Year Complete

2025

Value

$0.6 million

Size

Client

Southbase Construction

Contract Type

Supersub

Scope

Carpentry

Scope: Constructing substructure to support prefab buildings and constructing decking, stairs, ramps and canopies in front of prefab units. Schools included Howick Intermediate, Ormiston Junior College and Rosebank School.


Key Elements: Works were completed over the 2024-2025 holiday period. Changes to prefab module layouts were made weeks before they arrived so teams constantly were working to changing designs. For Howick school the deck modules were premade and craned into place to speed up works to ensure tight time frames were met. The canopies were introduced after the decks were complete and these works were carried out over first and second term 2 week holiday over 7 working days for all 3 schools.