Oratia School Hall

Oratia School Hall

Recladding

Location

Auckland

Year Complete

2025

Value

$0.2 million

Size

Client

Cook Brothers Construction

Contract Type

Supersub

Scope

Concrete & Carpentry

Scope: Removal of existing external cladding. Forming of new nib wall to external walls, replace rotten timber and treat rest of existing timber to walls and roof. Installation of new external cladding.


Key Elements: Installing a new NIB wall to the exterior walls which are load bearing supporting the roof meant temporary propping of the existing wall while the bottom was completely cut away while the NIB was poured. Once the nib was in place the bottom plate was reinstalled and existing studs connected. There was also a large amount of structural timber that required replacing so temporary propping was needed in multiple locations so these works could be completed.